State of Maine
Department of Environmental Protection
May 27, 1996
Ray Fortier
PO Box 621
Sabattus, ME 04280
RE: Canton Lake Dam & Water Levels
Dear Ray:
Thank you for coming in on May 22 to discuss the Canton
Lake situation with me. I will review here the Department's
position on the various issues we discussed.
Water Levels
I understand that all four dam gates were in place and
closed as of May 16, and that the lake is currently
rising. I will be visiting the dam on or about June 1 to
check on the water level. The Department reserves the
right to take enforcement action in the event that the
lake is not at or near the required June 1 target level
I also want to explain the Department's interpretation
of the 1978 water level order. The order says that, "After
April 15, the owner will regulate the flow out of
Anasagunticook [Canton] Lake to bring the water to the
maximum level set by [the Soil and Water Conservation
Commission] on or about June 1." The order sets the
maximum level at 5" below the topmost board in the gates.
It is my understanding that you have repaired several of
the gates so that they all now match their original
dimensions. It is also my understanding that, from your
experience, Canton Lake can rise significantly during
April and May even with all the gates fully open.
It is the Department's position that, under the 1978 order,
you must take appropriate and reasonable actions after
April 15 to bring the water level up to but not over the
target level of 5 inches below the top of the gates as
close to June 1 as possible. This does not mean that all
four gates should be closed on April 15. It does mean
that, based on your past experience with the dam and
expected runoff conditions, you should be opening and
closing gates as appropriate to meet the June 1 target.
What we lack right now is a plan describing how you will
manage gate openings and closings between April 15 and
June 1. Therefore, the Department hereby requests that
you prepare and submit such a plan for our review and
approval. Unless I hear otherwise from you, I will expect
this plan to be filed with us within 30 days of the date
of this letter.
The 1978 water level order also requires that, once the
maximum target level is reached, "the owner should not
manipulate the dam except to assure that the level does
not exceed the maximum level. Throughout the summer months,
the only lowering of the water below [the June 1 target
level] should be due to natural causes."
I understand that, as a practical matter, it is not possible
for any dam to be managed so that the water level stays
at exactly the same level throughout the summer. I also
understand that the water level in Canton Lake will
unavoidably drop during the summer due to evaporation,
leakage through the dam (which is required to maintain
a minimum stream flow), and water withdrawals by the
Canton Water District.
It is the Department's position that, under the 1978 order,
you must take appropriate and reasonable actions between
June 1 and October 31 to maintain the water level as close
as possible to the target level of 5 inches below the top
of the gates. The lake can vary within a reasonable range
above and below the target level as long as you are
opening and closing the gates in response to actual or
anticipated weather conditions. At the same time, you are
not responsible for non-compliance as a result of unexpected
events (for example, a surprise heavy thunderstorm or an
equipment failure or vandalism). What you are responsible
for is responding to unexpected events in a prompt and
reasonable way so that the water level target can again
be reached and maintained.
Dam Inspection
At our meeting, you asked whether you were still responsible
for complying with the results of the 1985 Dam Inspection
Report done for DEP. This report required, among other
things, that the dam owner prepare a written operation
and management plan for the dam, construct an earthen
flood control embankment along the impounded outlet stream
adjacent to Route 140, and construct an emergency overflow
spillway.
The DEP no longer has any authority over dam safety issues.
Therefore you are no longer responsible for complying
with the 1985 Dam Inspection Report. Dam safety is now
the responsibility of the Maine Emergency Management
Agency under a new dam inspection law passed in 1989.
I am enclosing for your information a letter we sent in
1989 to the Town of Canton (and copied to you) regarding
the dam safety issue. I am also enclosing a copy of the
1989 dam inspection law and MEMA's Chapter 3 Regulations
(Design and Construction Standards for New or Reconstructed
Dams). To my knowledge, MEMA has not to date inspected
the Canton Lake Dam to determine its appropriate hazard
classification or its physical condition. You should
contace MEMA directly (287-4080) if you have any questions
about dam inspection or safety issues.
Hydro Project/Land & Water Rights
I understand that you are still interested in pursuing
the development of a hydro-mechanical or hydro-electric
generating facility at the dam. As i explained to you,
any kind of hydro generating facility must be approved
by both the DEP and the Federal Energy Regulatory Commission.
In my May 3 letter to you, I explained the permiting
process and enclosed all the rules and application forms.
You can qualify for the FERC exemption process as long as
your project is rated at less than 5 megawatts capacity.
However. both DEP and FERC rules require that you own all
the land and water rights necessary for the construction
and operation of a hydropower project before you can get
the project approved. Neither DEP nor FERC can resolve
any property rights disputes that you may be involved in
with other land owners. Therefore, any property disputes
must be resolved before you can proceed with your project.
You also asked several questions about the nature of your
water rights and the rights of other people to boat up
and down the impounded outlet stream. These are not questions
that DEP can answer, because they involve issues of property
law that must eventually be answered by the courts if
disputes persist. However, I am enclosing a summary of
dams and water law that I pass out to the DEP staff and an
information digest titled "Access to Coastal and Inland
Waters" prepared by the University of Maine. I hope this
information is helpful.
Erosion Complaints
At out meeting, you said you had complaints about uncontrolled
erosion into the impounded stream due to nearby ground
disturbances. Please direct your complaints to Scott
Farwell of this office at 287-3901.
I am forwarding copies of this letter to the Canton Water
District, the Canton Lake Association, and the Towns of
Canton and Hartford so that everyone knows what the
Department expects of you.
Please call me at 287-3901 if you have any questions.
Sincerely,
Dana Paul Murch,
Dams & Hydro Supervisor
cc:
Bob Doucette, Canton Water District
Conrad Hutchinson, Canton Lake Association
Town of Canton
Town of Hartford
Scott Farwell, DEP
Back |
Lake Anasagunticook |
Home Page